For a generator that has been instructed to reduce output and is still waiting on compensation for the energy it could not sell, the queue handling that claim is now described by the transmission company itself as running at normal speed.
The National Transmission Company of South Africa is the country's transmission network service provider and system operator, the office that both instructs curtailment and assesses the claims that follow from it. Its media statement was published to the company's news page on 2 September 2026. The company says processing has been returned to normal operating levels within a committed timeframe, and that it did so by introducing streamlined processes.
Curtailment is what happens when the network cannot carry everything connected to it: a wind or solar plant is told to hold back output the grid cannot absorb at that moment. Under many connection and offtake arrangements the plant can claim for the production it lost, and each claim is assessed before any money moves. The implication is that the administrative step, not the entitlement, is what sits between a curtailment instruction and the cash it eventually produces for a generator or its lenders.
Read together, the statement speaks to the handling of claims and not to the volume of curtailment itself, which follows from grid reliability and from how much capacity the transmission network can carry at a given hour.
For anyone pricing curtailment risk into a project or a refinancing, two questions are left open. On this reading, they are whether normal operating levels hold as more connected renewable capacity comes online, and what the streamlined process asks of a claimant in evidence and in timing, since those together decide whether a compensation entitlement on paper behaves like a predictable receivable.
Source
- ntcsa.co.za /media-statement-ntcsa-restores-curtailment-claims-processing-to-normal-operating-levels-within-committed-timeframe-by-introducing-streamlined-processes